
Here You can read up on operational abilities in both the planning and construction phase
Pre – Construction
Schematic Design and Approval Phase:
| Development of a project budget |
| Document project organization and procedures |
| Development of a master schedule |
| Establish and monitor a detailed design |
| Schedule |
| Estimate design concepts and compare to cost models |
| Identify value engineering and life-cycle cost study areas |
Design Development and Approval Phase:
| Monitor the design development schedule |
| Review plans and specifications for technical accuracy and coordination of engineering disciplines. |
| Estimate final design development |
| Package |
| Identify long-lead items for early Purchasing |
| Identify pre-qualification criteria for contractors and suppliers |
Construction Document Phase:
| Establish final procurement strategies |
| Review plans and specifications for |
| technical accuracy and coordination of engineering disciplines |
| Recommend contract provisions |
| Prepare bid documents |
| Bid long-lead materials and equipment |
| Update master schedule |
| Establish and monitor detailed construction document schedules |
| Establish submittal procedures |
| Estimate final construction documents |
| Finalize pre-qualification of contractors and suppliers |
Bill and Award Phase:
| Prepare advertisements for bidding |
| Conduct pre-bid conferences |
| Manage issuance of addenda |
| Receive and analyze bids |
| Recommend award of contracts |
| Negotiate contracts |
Construction
Opening and Construction Phase:
| Maintain on-site staff |
| Manage testing agencies |
| Prepare detailed construction schedule |
| Monitor progress of the work |
| Control construction quality |
| Maintain jobsite records |
| Process pay requests |
| Recommend changes in the work |
| Process change orders |
| Coordinate processing of shop drawings |
| Conduct regular job meetings |
| Prepare field reports |
| Monitor safety program |
| Manage insurance program |
| Arrange photographic record of the project |
| Community and public relations – setup site |
| logistics plan by construction phase |
| Review plan with community at public meetings at the beginning of each phase |
| Set-up temporary facilities – service to site |
| Develop logistics plan consisting of: |
|
|
|
|
|
|
|
Close-Out Phase:
| Develop close-out schedule |
| Assemble operating manuals and Warranties |
| Coordinate acceptance inspections |
| Close-out construction contracts |
| Coordinate systems testing programs |
| Implement start-up procedures |
| Coordinate occupancy |
